Project Overview
In November 2024, the total plant area of Huashi Construction Group's Niassa Cement Plant in Mozambique reached 400 mu, with the first phase covering 200 mu. The cement production line with an annual output of 200,000 tons and the sand and gravel production line with an annual output of 1.2 million tons have been completed. After the start of trial production, all production lines will be gradually debugged and improved. At the same time, the plant is equipped with a high-voltage dedicated line and two dedicated transformers (2500KVA and 1000KVA respectively). The annual output of the concrete production line is 100,000 cubic meters and the annual output of the pipe pile and pole production line is 600,000 meters. Our company provides most of the power cables and wires